Prestigious Residential New Build – May Update

Bryburn were approached to build this luxurious five-bedroom home with guest accommodation. Project duration 80 weeks.

May Update

Internal decorations have now started on the first floor

Shallow pool is now waterproofed and the pumping station now installed

Ground floor tiling now fully completed

All plastering due to finish early June

Utility kitchen installed

We have now increased site security which includes a high tech CCTV system providing 24/7 monitoring.